Foundation stone laid for the 556-bedded district hospital, including a 50-bedded Cancer unit and a 100 bedded super specialty Cardiac Centre etc on 30.12.2008.
Estimated cost 92.66 crore, to be completed in 3 years or 36 months
Stipulated time of commencement 5/11/08
Stipulated time of completion: 4/11/11
Contractor: M/s M Venkata Rao Infra projects Pvt. Ltd,
Dona Paula.
Kirloskar consultant Ltd - PMC
NH17, construction site February 2009
Located at NH17 near South Goa District Collectorate, towards KTC bus Saand Margoa
https://flic.kr/p/7GFx6s
Feb 2009, construction site
The under-construction 400-bedded district hospital at Margao is estimated to cost Rs 150 crore including an amount required for the civil workshttps://flic.kr/p/7GFwbS
March 2011
193 crores including ancillary works like underground drainage, a shopping complex, development of parks, , residential quarters, landscaping etc.
Feb 2013
CM Parrikar said it will ready in 10 months
New district hospital ready by 19/12/13 he said at the time of new collectorate inauguration
Jan 2014
Ready by May 2015 - This announcement was made by chief minister Manohar Parrikar while inaugurating the Navelim panchayat ghar
https://flic.kr/p/nGgVMy
April 2014:
Health minister Laxmikant Parsekar has expressed hope of commissioning the new South Goa district hospital in Margao within the next 17-18 months.
https://flic.kr/p/q6GqsZ
https://flic.kr/p/nGrW85
23. 03. 2016
CM Parsekar says it will be ready by Nov 2016
He said it on site on 23.3.16
Dec 11 2016
After having failed to honour their promise of inaugurating the much- delayed under-construction Margao district hospital in December, chief minister Laxmikant Parsekar on Saturday assured that the hospital will now be completed by February 2017.
April 2017
Health minister Rane and TCP minister Vijay said the hospital will be ready by December 2017.
Again, New Health Minister Viswajit Rane on 29.4.2017 said the Hospital will be ready and inaugurated in April 2018
July 2017
Health Minister Rane said in the Assembly House that the hospital will be ready by May 2018
https://flic.kr/p/XuvwGS
https://flic.kr/p/Xuvv2N
Jan 21, 2018
Now CM Parrikar says it may be ready by May 2018 but it will be inaugurated in August with all equipment inside
https://flic.kr/p/FukDQQ
April 10, 2018
TCP Minister and local MLA Vijay Sardessai said that the new hospital likely to be commissioned by December 2018 or Dec 19 as per other news on 11.4.18
https://flic.kr/p/JTaQs8
23.6.18
Health Minister Viswajit Rane now says it will be commissioned in 6 months, (January 2019?)
https://flic.kr/p/25M7fdb
18. 1 2019
South Goa District hospital building ready by June 2019
and handed over to DHS it will then furnish it and ready to use / Occupancy /Inauguration by Sept 30,2019
Says GSIDC and Committee on Public undertaking that conducted inspection of the premises on 18.1.19
The Committee headed by Margao MLA Digambar Kamat, Nuvem MLA Wilfred de Sa, Cuncolim MLA Clafacio Dias, NT dtd 19.1.19
Pics March 2019
https://flic.kr/p/2e9ViaJ
https://flic.kr/p/24DhuFD
https://flic.kr/p/2e9VhJo
9.7.2019
Now, Margao MLA Digambar Kamat, Committee head said the hospital will be commission by October end 2019
26.7.2019 Goa Assembly floor
The Hospicio hospital will be commissioned in 4 months.
When ready, GSIDC will hand over to DHS by September 2019 total spent so far Rs.216 crores and another 30-35 crores required for improvements (Equipment?) after which the hospital will be inaugurated
Pic August 2019
13.8.19
https://www.flickr.com/photos/joegoauk27/48532608827/
https://www.flickr.com/photos/joegoauk27/48532453241/in/photostream/
https://www.flickr.com/photos/joegoauk27/48532454131/in/photostream/
https://www.flickr.com/photos/joegoauk27/48532452721/in/photostream/
Update: 29.10.2019
GSIDC now says it will be ready by November end (2019). TG of 30.10.19
it will then be handed over to DHS
Which could mean, the hospital will only be thrown open / commissioned / inaugurated in January 2020 or later
Update 17.12.19
GSIDC now says it will hand over by January 2020 end
which means Inauguration likely in March/April 2020
Update 24.1.2020
Hospital not ready to handover by end of January 2020 as stated above.
Slow work due to non payments to the contractors
Pics 24.1.20
https://www.flickr.com/photos/joegoauk36/49438885108/in/dateposted-public/
https://www.flickr.com/photos/joegoauk36/49439584262/in/photostream/
https://www.flickr.com/photos/joegoauk36/49439357891/in/photostream/
https://www.flickr.com/photos/joegoauk36/49438885108/in/photostream/
Update 29.03.2020
The Hospital (not inaugurated yet) is now declared as Quarantine Centre for ' Corona Virus Covid-19'
Fully operational Hospital likely after 15th March say CM
Update: 8.5.2020
OPDs (Out Patients Departments) from old Hospicio Hospital to start from New Hospital as from Monday 11.05.2020 followed by shifting of other departments, wards etc
Pics 23.5.20
https://www.flickr.com/photos/joegoauk50/49933554793/in/dateposted/
https://www.flickr.com/photos/joegoauk50/49934376877/in/photostream/
https://www.flickr.com/photos/joegoauk50/49934070716/in/photostream/
https://www.flickr.com/photos/joegoauk50/49933555588/in/photostream/
https://www.flickr.com/photos/joegoauk50/49934069986/in/photostream/
https://www.flickr.com/photos/joegoauk50/49933557743/in/photostream/
Update: 16.6.2020
Remaining wards of old Hospicio Hospital started shifting from 16.6.20 like medicine wards but shifting of operation theatre may take some time as it is still not ready? or need to be handed over to DHS by GSIDC, once ready
Update 19.8.2020
The South Goa District Hospital likely to be fully operational by 1st September 2020
GSIDC to hand over to DHS by 25th August 2020 as they were given 30 days deadline to handover.
Four operation theatres OT already commissioned and another four OTs will be ready by 22nd August 2020 and the remaining three (OTs) will be commissioned by 28th August 2020. (11 OTs).
Old Hospicio hospital will be used as Covid Hospital for pre-natal and Ante -natal patients as from September 2020
NT pg2 20.8.20
Update 8.9.2020
The New Hospital is now Covid Hospital eff.11.9.20
Due to rising Corona / Covid-19 cases in Goa, the Government converting the Margao South Goa District Hospital into a dedicated Covid Hospital.
Goa has 3 other Covid hospitals Viz ESI Margao since March 27, Ponda Sub District Hospital since August 12 and GMC Bambolim for extremely Covid critical patients in 3 wards no. 145, 146 and 147 since August 24. Besides, old Hospicio for Pre-natal and ante natal Covid patients (this may also shift to new hospital)
New South Goa District Hospital likely to operated as Covid Hospital from Friday 11th September 2020. In the mean time, all OPDs, Male/Female wards etc from new hospital are being shifted back to old Hospicio Hospital.
New SGDH Covid Hospital to start from 19th Sept. 2020 says Health Minister Rane on 13.9.20
Missed, missing deadlines so far
Stipulated time of completion: 4/11/11 - Congress
New district hospital ready by 19/12/13 - Parrikar
Ready by May 2015 - Parrikar
CM Parsekar says it will be ready by Nov 2016
hospital will now be completed by February 2017 - Parsekar CM
Hospital will be ready by December 2017 - Health Minister Rane
Hospital will be ready and inaugurated in April 2018 - Health Minister Rane
Hospital will be ready and inaugurated in January 2019 - Minister Rane
Ready by June 2019, inauguration by Sept 30, 2019 GSIDC, Committee Kamat
Margao MLA Kamat, Committee head said the hospital will be commissioned by October end 2019
The Hospicio hospital will be commissioned in 4 months - by November 2019 - Assembly floor
GSIDC says it will be ready by November end (2019)
GSIDC now says it will hand over to DHS by January end 2020
CM Sawant said in the Assembly House on 5.2.2020 that contractors will be paid before March and that work will be completed in 2 months (after payments to contractors) which could mean the new hospital will be ready to inaugurate only after June ?
March 2010 Photo
www.flickr.com/photos/joegoauk23/4398511366/
Old /
existing Hospicio, Margao
Hospicio do Sagrado Coracao de Maria
Completes 150 years of existence in 2018.
The hospital was started by Fr Antonio Joao de Miranda
Hospicio do Sagrado Coracao de Maria
Completes 150 years of existence in 2018.
The hospital was started by Fr Antonio Joao de Miranda
Pic 2006
https://www.flickr.com/photos/joegoauksix/331589767
Pic January 2013
https://flic.kr/p/dNdF9T
https://flic.kr/p/npYTbi